The construction method of acrylic flooring

The construction method of acrylic flooring


Preparation foundation: Clean up debris, grave on the site to ensure that the foundation is flat, and carry out the necessary filling and compaction.

Laying the bottom layer: lay a layer of concrete or asphalt, usually 5-10 cm thick.

Mix the material in proportion: Mix SSG sports’ acrylic pigments, adhesive 108, cement, sand and water in proportion to make a uniform resurfacer.


















Spray primer: Apply a layer of primer on the surface of the underlying concrete or asphalt




Apply the acrylic resurfacer: Apply the mixed acrylic paint evenly on the surface of the primer,use professional tools to flatten and compact the coating surface
Secondary scraping: After the first layer of paint is dried, apply the same layer of acrylic paint to improve durability and aesthetics.




Apply top coat : Scrape Acrylic Surface Color Layer with inner and outer court separated



Line making: draw the line after the surface dried.


Completed: After the surface and line is fully dried and the necessary cleaning work is carried out, the construction of the hard acrylic floor of the tennis court is completed.
Notes:
 
1. Construction should avoid severe weather conditions such as high temperature and strong wind.
2. Before construction, the quality and storage time of the coating should be checked, and the products that meet the standards should be selected.
3. Before construction, you should carefully read the product manual and operating specifications to ensure that the construction follows the correct steps.